Royal Tide will begin the community-wide pressure washing project on Monday, August 17. The project is expected to take approximately 10–12 days, weather permitting, and has been divided into five work zones. Each zone is anticipated to take one to two days to complete. Residents are reminded that street parking will not be permitted during their zone's scheduled work dates and should ensure all vehicles are parked completely within their driveways.
To view the zone map, project schedule, and important resident information, please click here.